Parents » Construction Updates

Construction Updates

 
We are excited to announce that construction is set to begin at the beginning of April! Please see the file below for a tentative schedule. 
 
We will provide regular updates as construction begins. 
 
 
Updated Planning Schedule
 
Green cells are areas ahead of the original scheduled dates. Yellow cells are slight schedule extensions from the original scheduled dates. 
 
Updated Schedule
 
 
 
Updates
 
 
July 28, 2023
 
 
July 21, 2023
 
 
Please click the video to view the photo slideshow.
 
June 30, 2023
 
 
June 8, 2023
 
Updated floor plans
 
Please see the construction plans at the bottom of this page for updated plans.
 
 
May 30, 2023
 
Updated Planning Schedule
 
Green cells are areas ahead of the original scheduled dates. Yellow cells are slight schedule extensions from the original scheduled dates. 
 
Updated Schedule
 
 
 
April 27, 2023
 
Groundbreaking Ceremony
 
 
 
April 12, 2023
 
Due to the construction project there are some minor, but significant adjustments being made to the traffic pattern for morning pick-up and afternoon drop-off. The safety of our students, staff, and families is our top priority as the construction team begins work on this project. 

Please follow the traffic pattern outlined on the attached map. 
  • The dark green arrows show the direction that all traffics should proceed on campus. 
  • The light green arrows indicate the pick-up and drop-off traffic pattern for mornings and afternoons. 
  • All traffic will need to enter at the blue entrance marked "ENTER" on the map and exit at the "EXIT ONLY" area marked with the red. 
  • There is no parking for families in the yellow highlighted area. That parking is designated for construction crew only. 
    • Please do not attempt to enter at this location or park here. Please review the attached map for visual reference. 
Also, remember that there is no parking along the driveway during drop-off and pick-up times. Please use the crosswalks in the mornings and afternoons rather than crossing the parking lot in oncoming traffic. It is imperative that everyone follows these procedures in order to maintain a safe and smooth experience for all. 

Thank you for your continued support and partnership with Belle Creek!
 
Construction Traffic Map
 
April 7, 2023
 
We will be holding a groundbreaking ceremony on Thursday, April 27th at 3:45pm on the Northwest side of the building in the parking lot area. Join us to celebrate the start of construction for the new building additions!

The event will also be live-streamed on the Belle Creek Facebook page for families not able to attend in person
 
 
March 15, 2023
 
We are excited to announce that our building project for Belle Creek has been moving along in the background during this current school year. We will soon have our necessary permits to begin breaking ground and our much-anticipated construction will begin soon. The early impact should be minimal, but there may be an impact on the average school day and your student. 

Upcoming Changes to Campus

Beginning April 1st, staff will be utilizing the main parking lot as staff parking. This will impact the number of available parking spots. Please plan for extra time for parking if using the school parking lot at pick up times. 
 
During the week of Spring Break, GTC will be installing portable chain link fencing around areas of the campus that construction will begin first. The fencing will go around: the 3rd-6th grade entrance by the playground and the grassy mound outside the main office. Please reference the construction map for precise fence location.
 
The following changes will occur due to the fencing: 
      • Parts of the playground will be blocked off or have a limited use. 
      • The 3rd-6th grade entrance will be blocked off by fencing and unusable. 
        • The 3rd-6th grade entrance and exit will be moved to the Library Entrance (Door 2). 
 
There should not be an impact to entering and exiting the main building entrance or other campus usage. 

Construction
    • Work will begin on the 2-story classroom addition and the new office complex simultaneously. 
    • The stage bump-out will not begin until the summer break.
      •  The cafeteria/MS exit will not be affected during the remainder of this school year. 
    • All work until this Spring will be outside foundation work and framing the new buildings.
    • There will be no construction inside the existing school building space during the remainder of the school year. 
There should be little or no other impact to regular classroom activities inside the building. The goal is also to have little or no impact on traffic patterns for parents around the driveways of the campus for before or after school pick-up.
 
It's time to get excited about this project as go-time is finally here!
 
 
 
March 3, 2023
 
Planning Schedule
 
Planning Schedule
 
 
 
 
Thank you to the Brighton Community for approving the 2021 5A Bond! 
 
Belle Creek Charter School was granted $5.9 million dollars to fund new construction and improvements to the school!
 
The funding will help us in adding:
  • A new 2-story classroom addition that will include a STEM and Life Skills Classroom, a new Art classroom with a kiln, and New General Music and Choir Classroom. 
  • A new addition to the cafeteria with a larger band classroom and a stage for performances. 
  • A new administrative area with a more secure Main Entrance, a health office, and Board conference room. 
  • An additional restroom in the Kindergarten classrooms. 
 
The project will also include:
  • Renovations to the current administrative offices for relocation of the Special Education Department offices, a new Training Room, and a Staff Lounge. 
  • Renovations to the current Special Education offices for additional RTI and small group rooms, storage, and a lactation room. 
  • Renovations to the current band classroom for a conference room. 
 
 
Construction Plans
(Please note construction plans may not reflect the most recent plans)